Havnevej 33, DK 3300 Frederiksvaerk - Phone: +45 4777 0333 - Fax: +45 4777 0302 - Mail: info@dansteel.dk
You are here: 15 April 2015 - Verification audit of NLMK DanSteel A/S's CO2 emissions for the year 2014 successfully completed

Search on Site

Latest news

- 12 August 2016 - NLMK DanSteel participates in ONS 2016
in Stavanger, Norway 29 August-2 September 2016

- 4 April 2016 - NLMK DanSteel A/S participated in the 2nd Steel Plates Conference Europe
- 12 February 2016 - NLMK DanSteel A/S hosted the Danish Marine & Offshore Group (DMOG) Annual Meeting
- 12 February 2016 - NLMK DanSteel A/S received four certificates
- 20 January 2016 - NLMK DanSteel A/S host the DMOG annual general meeting the 28 January 2016
- 7 August 2015 - NLMK DanSteel A/S participates in Offshore Europe 2015 in Aberdeen, UK
- 7 May 2015 - New film about special steel for wind energy
- 15 April 2015 - Verification audit of NLMK DanSteel A/S's CO2 emissions for the year 2014 successfully completed
- 6 February 2015 - NLMK DanSteel participates in EWEA OFFSHORE 2015 EVENT
- 9 January 2014 - NLMK DanSteel certifies Occupational Health and Safety and Environmental Management Systems
- 19 November 2013 - Danish Minister of Trade visits NLMK DanSteel
- 14 November 2013 - NLMK DanSteel, Technical Universities of Denmark and Lipetsk, and the Halsnaes Municipality join efforts to achieve process excellence in production of thick plates for offshore constructions
- 23 September 2013 - Yuriy Bokachev appointed Managing Director of NLMK DanSteel A/S
- 24 April 2013 - New rolling stand at NLMK DanSteel A/S
- 21 March 2013 - Earth Hour 2013
- 20 December 2012 - NLMK DanSteel A/S completes revamping of its rolling mill
- 25 October 2012 - Oleg Bagrin Elected President of NLMK
- 8 August 2012 - Mill housings for New rolling mill arrived
- 25 May 2012 - Press release
Annual Report 2011

- 20 December 2011 - Audit of NLMK DanSteel A/S' Management Systems
- 18 November 2011 - NLMK DanSteel A/S nominated for Nordea Business Award 2011
- 26 August 2011 - Press release - DanSteel A/S changes name and logo
- 2 May 2011 - Press release - Annual Report 2010
- 2 March 2011 - New Rolling Mill
Multi-million worth investment

- 22 September 2010 - New Area Sales Manager
- 27 August 2010 - Summer stop
- 14 July 2010 - The gate house increases its opening hours
- 12 July 2010 - The thick plate centre is now working
- 24 February 2010 - New video presentations
- 18 January 2010 - Recertification of DanSteel A/S' Management Systems
- 3 December 2009 - DanSteel A/S has received 60-tonnes slabs
- 12 November 2009 - Disposal site from the Danish Steel Works A/S is to be removed
- 10 November 2009 - Thick Plate Centre
- 5 November 2009 - Cutting of motherslabs
- 1 October 2009 - New Test House
- 1 October 2009 - Recognition of the Quality Assurance System at DanSteel A/S
- 1 September 2009 - New noise barriers at DanSteel A/S
- 26 September 2008 - New thickness gauge

 

 

    Havnevej 33, DK 3300 Frederiksvaerk - Phone: +45 4777 0333 - Fax: +45 4777 0302 - Mail: info@dansteel.dk

Verification Audit of NLMK DanSteel A/S's CO2 emissions for the year 2014 successfully completed

NLMK DanSteel A/S is pleased to announce that the company's work with monitoring and control of fuel consumption and thus CO2 emissions was approved in connection with the periodic verification audit conducted by Det Norske Veritas (DNV GL-Business Assurance Denmark A/S) on 5 March 2015.

The results were subsequently reported to the Danish Energy Agency on 25 March 2015.

The verified CO2 emission data have been transferred to the Danish Emission Trading Register and are approved to have been verified. Based on the fulfilled obligations NLMK DanSteel A/S will be assigned free CO2 allowances for 2015 emission. Due to significant energy improvements and the increased production the key figures for the total gas consumption in 2014 are lower than in 2013. Similarly, the electricity consumption has been to a large extent reduced as a result of the implemented efficiency improvement projects. This has led to the reduction of CO2 emissions by 8 %.

The Climate Strategy has been revised and the goal for 2015-2017 approved.

Irina Volovick
Energy Manager

Page updated 15 April 2015